Distribution Impact Analysis Tool
27%
Canada's EV fleet grew 27% in 2025
39%
London's new EV registrations rose 39% in one quarter
Source: Statistics Canada, "A pan-Canadian electric feel" (September 2026). Fleet growth calculated from registered zero-emission vehicles, 2024 to 2025; London figure is new registrations, Q1 to Q2 2026.
Four numbers are all you need. Everything else has sensible defaults under More Scenario Settings.
The feeder or transformer rating. Your planning team will have it.
Last year's peak demand on this feeder, before new EVs.
Residential customers served by this feeder.
"What happens to my feeder when 20% of homes have EVs?"
Enter the level you want to check, e.g. 20%.
Already have EVs on this feeder? Enter today's share under More Scenario Settings → Adoption Timeline → Current EV share. It sets when you reach this level and the year you run out of capacity.
Assumes a 35% feeder EV coincidence, meaning 35% of EV chargers on the feeder are expected to be drawing power at the same time during the evening peak.
Models 150kW DCFC units with a 50% diversity factor, meaning about that share of fast chargers are expected to be in use at the same time.
How many homes on this feeder have an EV today. Sets when you reach the EV share you're testing and the year you run out of capacity.
Reference: zero-emission vehicles were 3.5% of Canada's 25.3 million registered light-duty vehicles in 2025, up from 2.8% in 2024 (Statistics Canada). Ontario trails the national average, so 5% of homes is a reasonable starting point; use your own data if you have it.
Compounding yearly growth, capped at 100% of homes.
Reference: Canada's registered zero-emission vehicle fleet grew by about 27% in 2025 (+189,803 vehicles) and 44% in 2024 (+212,473), calculated from Statistics Canada figures. Growth slowed in 2025 after federal incentives were paused, so 25% is a reasonable default.
Non-EV growth such as new connections and heat pumps.
Via time-of-use rates or managed charging programs. 0% = uncontrolled.
The whole feeder at peak, using the conservative default feeder EV coincidence (35%). Settings: More Scenario Settings → Advanced Assumptions.
Peak load with EVs
0 kW
Spare capacity
0 kW
Runs out of capacity
–
Based on current EV share and growth (More Scenario Settings)
| Homes with EVs | Peak with EVs | Spare / over | Transformers at risk | Status |
|---|
Status at each EV share today. The verdict above also considers the year the feeder runs out of capacity.
Beyond the feeder
Many secondary conductors and service drops were sized decades ago, before homes added EV chargers, hot tubs, saunas and heat pumps. Today those loads can push older secondaries past their rating, and some are overheating and melting in service. A single Level 2 EV charger draws 7–11 kW on its own.
Local transformers at risk
–
Homes served by a typical pole-top or pad-mount unit.
Common pole-top sizes: 25, 37.5, 50, 75, 100 kVA.
Peak per home is the diversified evening demand of a home without an EV. The 5 kW default is conservative; Ontario planning guidance often uses 2.5–4.5 kW.
The share of EVs on one transformer (typically 4–8) charging at the same moment. Small groups have little diversity, so planners use 70–80%. Set 100% for a stress test, for example when assessing ageing transformers for replacement. This is separate from the feeder EV coincidence.
How GenCore helps
Identify
A power system study measures today's real load on your secondaries and finds the sections that are overloaded.
Plan
A prioritized plan ranks which sections to address first, so budgets go where the risk is highest.
Manage & replace
We engineer the upgrades, from conductor and transformer sizing to replacement designs, and help manage load in the meantime.
This is a thermal screening tool. It uses simple diversity factors rather than a load-flow model, so results are fast and transparent. Every assumption below can be adjusted under Advanced Assumptions.
EV adoption and growth
Charging power and coincidence
Ontario regulation and planning
Engineering standards (checks beyond this screen)
Talk to an engineer
GenCore Utilities helps utilities plan for EV growth with detailed power system studies, including load flow, short circuit studies, protection & coordination, and Arc Flash studies modelled on your actual network.
Questions about your results? Send us a note. Your screening results are included automatically.
Prefer email? Contact info@gencoreutilities.com. See how we handle your information in our .
Disclaimer: This tool provides a preliminary thermal capacity estimation based on simplified load diversity assumptions. It does not account for localized voltage drop, phase imbalance, or secondary transformer constraints beyond the simplified screen above. GenCore Utilities Ltd. assumes no responsibility for capital planning decisions made solely on these preliminary results. A full power system study, including but not limited to Load Flow, Short Circuit, and Protection and Coordination, is required for accurate grid planning.